Mobilising a Drill Rig to a Remote Mine Site: A Practical Checklist
Access, pads, fuel, water, safety and paperwork: what to have ready so the rig starts drilling the day it arrives.
NIKHI GROUP · 11 November 2026

The most expensive day of a drilling campaign is the day the rig arrives and can't start. A little preparation on site avoids it.
Access
- Confirm the route from the nearest main road, including bridges, river crossings and tight turns.
- Tell us whether the last stretch suits a truck mount or needs a crawler (see crawler or truck-mounted).
Drill pads
- Prepare level, compacted pads large enough for the rig and the compressor.
- Rigs level themselves on hydraulic jacks (the PRD OZ RC has four), but they still need firm ground.
Fuel and water
- Plan fuel supply for the rig and compressor for the length of the campaign.
- If the programme uses water or foam injection, plan a water source and storage.
Safety
- Brief the crew on site rules, emergency contacts and the nearest medical facility.
- Mark exclusion zones around the rig. Check that rig safety equipment (fire suppression, emergency stops, guards) is in place on arrival.
Paperwork
- Have permits, site access approvals and any import or transit documents ready before the rig moves.
Communications
- Agree a daily contact and reporting routine: metres drilled, hours, issues.
Planning a campaign? Send us the site location and dates below and we'll plan the rig around them.
Rental quote
Request a rig rental quote
Tell us about your project and we'll reply with availability, the right configuration and pricing.